# The Stonestreet Green Solar Order 2025, Paragraph 12: Operational management plan

Extent: E+W+S

(1) Prior to the operation of the authorised development, an OMP must be submitted to and approved by the local planning authority, such approval to be in consultation with the relevant statutory nature conservation body and the Environment Agency.
(2) The OMP must be in accordance with the outline OMP.
(3) The OMP must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development to which the OMP relates.

---
Source: https://www.legislation.gov.uk/uksi/2025/1175/schedule/2/paragraph/12 (the official version)