# The Stonestreet Green Solar Order 2025, Paragraph 17: Applications made under requirements

Extent: E+W+S

(1) Where an application has been made to the local planning authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, or for any consent, agreement or approval further to any document referred to in any such requirement, the local planning authority must give notice to the undertaker of its decision on the application within a period of eight weeks beginning with—
(a) the day immediately following that on which the application is received by the local planning authority; or
(b) where further information is requested under paragraph 18 the day immediately following that on which the further information has been supplied by the undertaker, or such longer period as may be agreed in writing by the undertaker and the local planning authority.
(2) In determining any application made to the local planning authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, the local planning authority may—
(a) give or refuse its consent, agreement or approval; or
(b) give its consent, agreement or approval subject to reasonable conditions,
and where consent, agreement or approval is refused or granted subject to conditions the local planning authority must provide its reasons for that decision with the notice of the decision.

---
Source: https://www.legislation.gov.uk/uksi/2025/1175/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.