  "heading": "Expiry of development consent",
  "text": "(1) The authorised development must cease generating electricity on a commercial basis no later than the 40th anniversary of the first export date.\n(2) Confirmation of the first export date must be provided by the undertaker to the local planning authority within one month of its occurrence.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 2 in force at 13.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1175/schedule/2/paragraph/2",
    "retrieved_at": "2026-10-28T21:09:52.508378+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}