# The Stonestreet Green Solar Order 2025, Paragraph 4: Detailed design approval

Extent: E+W+S

(1) No phase of the authorised development may be commenced until written details of—
(a) the layout;
(b) scale;
(c) proposed finished ground levels;
(d) external appearance;
(e) hard-surfacing materials;
(f) vehicular and pedestrian access, parking and circulation areas;
(g) refuse or other storage units, signs and lighting;
(h) power and communications cables and pipelines;
(i) fencing and other means of enclosure;
(j) security measures; and
(k) acoustic barriers,
relating to that phase have been submitted to and approved by the local planning authority.
(2) The written details that are submitted for approval pursuant to sub-paragraph (1) must accord with the design principles.
(3) The authorised development must be carried out in accordance with the details approved pursuant to sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2025/1175/schedule/2/paragraph/4 (the official version)
Page: https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-2/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.