{
  "url": "https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-2/paragraph-6",
  "json_url": "https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-2/paragraph-6.json",
  "legislation": "uksi/2025/1175",
  "legislation_title": "The Stonestreet Green Solar Order 2025",
  "legislation_url": "https://openlegislation.uk/stonestreet-green-solar-order-2025",
  "path": "schedule/2/paragraph/6",
  "kind": "paragraph",
  "number": "6",
  "heading": "Construction environmental management plan",
  "text": "(1) No phase of the authorised development may commence until a CEMP for that phase has been submitted to and approved by the local planning authority, such approval to be in consultation with the relevant statutory nature conservation body, Environment Agency and Kent County Council.\n(2) The CEMP for each phase of the authorised development must be in accordance with the outline CEMP.\n(3) All construction works associated with the authorised development in each phase must be carried out in accordance with the approved CEMP for that phase.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 6 in force at 13.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1175/schedule/2/paragraph/6",
    "retrieved_at": "2026-10-28T21:09:52.508378+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}