  "url": "https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-6",
  "json_url": "https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-6.json",
  "legislation": "uksi/2025/1175",
  "legislation_title": "The Stonestreet Green Solar Order 2025",
  "legislation_url": "https://openlegislation.uk/stonestreet-green-solar-order-2025",
  "path": "schedule/6",
  "kind": "schedule",
  "number": "6",
  "heading": "ACCESS TO WORKS",
  "text": "(1) Area\n(2) Street\n(3) Description of means of access\nAshford Borough Council\nBank Road #1 southbound\nThe provision of a permanent means of access to the authorised development from the point marked A-1 on sheet 6 of the streets, rights of way and access plans.\nAshford Borough Council\nLaws Lane #1 westbound and eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-2 on sheet 6 of the streets, rights of way and access plans.\nAshford Borough Council\nLaws Lane #2 westbound\nThe provision of a permanent means of access to the authorised development from the point marked A-3 on sheet 6 of the streets, rights of way and access plans.\nAshford Borough Council\nLaws Lane #3 eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-4 on sheet 6 of the streets, rights of way and access plans.\nAshford Borough Council\nBank Road #2 southbound\nThe provision of a permanent means of access to the authorised development from the point marked A-5 on sheet 6 of the streets, rights of way and access plans.\nAshford Borough Council\nBank Road #3 northbound\nThe provision of a permanent means of access to the authorised development from the point marked A-6 on sheets 6 and 7 of the streets, rights of way and access plans.\nAshford Borough Council\nPublic right of way AE396 #1 westbound and eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-7 on sheets 6 and 7 of the streets, rights of way and access plans.\nAshford Borough Council\nPublic right of way AE396 #2 westbound and eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-8 on sheets 6 and 7 of the streets, rights of way and access plans.\nAshford Borough Council\nPublic right of way AE396 #3 westbound and eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-9 on sheet 6 of the streets, rights of way and access plans.\nAshford Borough Council\nBank Road #4 northbound and southbound\nThe provision of a permanent means of access to the authorised development from the point marked A-10 on sheets 6 and 7 of the streets, rights of way and access plans.\nAshford Borough Council\nCalleywell Lane #1 westbound\nThe provision of a permanent means of access to the authorised development from the point marked A-11 on sheet 7 of the streets, rights of way and access plans.\nAshford Borough Council\nCalleywell Lane #2 westbound\nThe provision of a permanent means of access to the authorised development from the point marked A-12 on sheet 7 and 8 of the streets, rights of way and access plans.\nAshford Borough Council\nStation Road #1 eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-13 on sheets 7 and 8 of the streets, rights of way and access plans.\nAshford Borough Council\nStation Road #2 eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-14 on sheets 7 and 8 of the streets, rights of way and access plans.\nAshford Borough Council\nStation Road #3 eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-15 on sheet 8 of the streets, rights of way and access plans.\nAshford Borough Council\nGoldwell Lane eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-16 on sheet 9 of the streets, rights of way and access plans.\nAshford Borough Council\nChurch Lane westbound and eastbound\nThe provision of a permanent means of access to the authorised development from the point marked A-17 on sheet 10 of the streets, rights of way and access plans.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 6 in force at 13.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1175/schedule/6",
    "retrieved_at": "2026-10-28T21:09:52.508378+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}