Regulation 4 Notices
An undertaker executing street works (other than minor works) in a highway to which these Regulations apply shall give the approved authority notice in writing of the beginning of those works specifying by reference to the National Street Gazetteer the street or streets in which the works are to be carried out (“actual start of works notice”) not later than the end of the day following the day on which the works begin.
An undertaker executing minor works in a highway to which these Regulations apply shall give the approved authority a daily notice in writing of those works in the form of the daily whereabouts for minor works notice in Appendix D or Appendix E to the Co-ordination Code specifying by reference to the National Street Gazetteer the street or streets in which the works are being carried out (“daily whereabouts notice”), the first such notice to be given not later than the end of the day before the day on which the works begin.
When an undertaker has completed interim reinstatement of a highway and has removed all remaining spoil and unused materials together with all signing, lighting and guarding, and has returned the highway fully to public use he shall give the approved authority notice thereof in writing (“works clear notice”) not later than the end of the day following the day on which the highway was returned fully to public use.
When an undertaker has completed permanent reinstatement of a highway and has removed all remaining spoil and unused materials together with all signing, lighting and guarding, and has returned the highway fully to public use he shall give the approved authority notice thereof in writing (“works closed notice”) not later than the end of the day following the day on which the highway was returned fully to public use.