Regulation 5 Prescribed charges and prescribed periods

Original text. Later amendments are not shown.

(1)

A highway authority shall, subject to paragraph (8), require an undertaker to pay the prescribed charge where the duration of street works carried out by the undertaker in a maintainable highway to which these Regulations apply exceeds the prescribed period or a reasonable period, whichever is the longer.

(2)

Paragraph (1) does not apply to the following works—

(a)

works which do not require breaking up the street,

(b)

repairing, resetting or replacing manhole or chamber covers or frames,

(c)

replacing poles, lamps, columns or signs in the same location,

(d)

pole testing.

(3)

The duration of street works includes any period during which an undertaker is carrying out remedial works required by an authority pursuant to section 72(3) of the Act.

(4)

The prescribed charge shall be a charge as set out in this paragraph for each day (or part of a day) during which the street works in each and every street mentioned in the actual start of works notice, or, in the case of minor works, in the first daily whereabouts notice, continue beyond the prescribed period or a reasonable period, whichever is the longer:

(a)

for minor works, emergency works and urgent works in road category Types 3 and 4, £100;

(b)

for standard works in road category Types 3 and 4, £250;

(c)

for minor works, emergency works and urgent works in road category types other than Types 3 and 4, £500, and

(d)

for standard works in road category types other than Types 3 and 4, £2,000.

(5)

Works shall be treated as beginning, for the purposes of paragraphs (4) and (7), on the date given in the actual start of works notice or the first daily whereabouts notice, as the case may be.

(6)

Works shall be deemed to continue for the purposes of paragraph (3) until a works clear notice or a works closed notice (as the case may be) has been given in respect of those works.

(7)

The prescribed period shall be 3 days starting on the day on which the works begin.

(8)

A highway authority may reduce the amount, or waive payment, of a charge in any particular case, in such classes of case as they may decide, or in all cases other than a particular case or such class of case as they may decide.

(9)

Charges may only be made in respect of works of which notification has been given by notice pursuant to the Act relating to such works that they are to be executed in a street or streets identified as that street or those streets are identified in the National Street Gazetteer.

(10)

Charges are only payable in respect of street works where the highway authority have given the undertaker, not later than six months after receipt of a works clear notice or a works closed notice (whichever is the earlier), an account in writing setting out the charge payable.