Regulation 7 Further and revised estimates of duration of works

Original text. Later amendments are not shown.

(1)

If it appears to an undertaker that, by reason of matters not previously foreseen or reasonably foreseeable, the duration of the works—

(a)

is likely to exceed the prescribed period,

(b)

is likely to exceed the period stated in his previous estimate, or

(c)

is likely to exceed the period previously agreed or determined under section 74(2) of the Act to be a reasonable period,

he shall give to the authority notice in writing containing an estimate or revised estimate.

(2)

Where a notice in writing containing an estimate or revised estimate is submitted under paragraph (1) any previous estimate, agreement or determination shall cease to have effect and the period stated in the new estimate shall be taken to be agreed by the highway authority to be reasonable unless they give notice in writing to the undertaker within 3 days of receipt of the estimate or revised estimate that they object.

(3)

A notice by an authority under paragraph (2) shall contain their own estimate of the period of duration.