# The Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (England) Regulations 2009, Regulation 7: Prescribed period

Extent: E+W

In relation to an undertaker executing street works in a highway to which these Regulations apply, the period prescribed under section 74(1)(a) of the 1991 Act shall be two working days, starting on the date on which the works begin.

---