# The Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (England) Regulations 2009, Regulation 8: Duration of works

Extent: E+W

For the purposes of these Regulations, the duration of street works will only come to an end when the undertaker has—
(a) completed interim reinstatement, or as the case may be permanent reinstatement, of a highway;
(b) removed—
(i) all signing, lighting and guarding, and
(ii) all remaining spoil, unused materials and other plant; and
(c) returned the highway fully to public use.

---