# The Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (Wales) Regulations 2009, Note: Explanatory note


(This note is not part of the Order)
These Regulations provide for the payment of charges to highway authorities where certain street works, executed by undertakers in maintainable highways, are unreasonably prolonged.
Regulation 5(1) and (2) require an undertaker, executing street works in a highway to which these Regulations apply by virtue of regulation 4, to give an “actual start of works notice” within the periods set out. Regulation 5(3) and (4) specify the period within which a “works clear notice” must be given following the completion of an interim reinstatement of the highway and within which a “works closed notice” must be given following permanent reinstatement.
Regulation 6 establishes the “prescribed period” for the purposes of section 74(1)(a) of the 1991 Act and regulation 7 specifies when works end for the purpose of calculating any overrun charges.
Regulation 8 prescribes the charges payable where the duration of street works exceeds the longer of the prescribed period or a reasonable period, subject to certain exemptions. Different daily rates will apply depending upon the category of street works and the type of street in which they are carried out. Where remedial works are carried out, any overrun will be charged as if those works were in the same category as the works being remedied. For this purpose, provision is made for treating older works as being within contemporary categories of street works. Where the duration of works would not have overrun but for the presence of a single item of signing, lighting or guarding, the charge will consist of a single payment of £100 provided the undertaker removes it within the specified time limit following the highway authority’s request to do so. Provision is made for the reduction or waiver of a charge in various cases.
Regulations 9 and 10, which do not apply where a permit to carry out street works is required, enable an undertaker to provide the highway authority, in certain circumstances, with an estimate or revised estimate of the duration of works, which may be taken to be agreed as a reasonable period in the absence of an objection.
Regulation 11 provides for the application of charges and the keeping of accounts. Regulation 12 creates an offence of failing to give any notice required by the Regulations.
Regulations 13 and 14 prescribe the form of any notice and the manner in which it must be served.
An impact assessment of the effect that this instrument will have on the costs of business and the voluntary sector is available from (insert web address).

---
Source: https://www.legislation.gov.uk/wsi/2009/1268/note (the official version)
Page: https://openlegislation.uk/street-works-charges-for-unreasonably-prolonged-occupation-of-the-highway-wales-regulations-2009/note
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.