# The Street Works (Registers, Notices, Directions and Designations) (Wales) Regulations 2008, Regulation 8: Advance notice of works


(1) For the purposes of section 54, an undertaker must give not less than three months' advance notice of major works, except where such works are —
(a) the subject of a notice under section 55(1) given in accordance with regulation 9(3) and in respect of which no notice has already been given under this paragraph; or
(b) notified under paragraph 2(1)(d) of Schedule 3A to the 1991 Act.
(2) For the purposes of section 54(4A), the period prescribed is 2 days beginning with the starting date specified in the notice.
(3) For the purposes of section 54(4B), the period prescribed is 15 days.

---
Source: https://www.legislation.gov.uk/wsi/2008/101/regulation/8 (the official version)
Page: https://openlegislation.uk/street-works-registers-notices-directions-and-designations-wales-regulations-2008/regulation-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.