Regulation 7
In a case where works consist of or include major bridge works an undertaker shall not be liable for costs in respect of the provision of adequate space in the structure of the bridge or of sufficient strength in the bridge to accommodate the undertaker’s apparatus in the bridge, but this paragraph shall not apply to the cost of any ducts, pipe bays, hangers or other provision for housing or supporting the apparatus within such space or to the provision of adequate space or adequate strength to accommodate the apparatus of any undertaker installed in the bridge after the execution of such works other than the installation, replacement or modification (not involving enlargement) of apparatus previously installed in the bridge prior to the execution of such works.
No costs shall be allowable to an undertaker in respect of apparatus placed in the street after the authority has given to the undertaker notice pursuant to section 85(2)(a) of the Act of their intention to execute the works:—
in the case of works consisting of major bridge works comprising a replacement of the bridge, not more than 10 years before those works are executed;
in the case of any other works, not more than 5 years before those works are executed.