# The Submarine Pipe-lines (Designated Owners) (No. 19) Order 1989, Part II: DESCRIPTION OF PIPE-LINES


(1)
(2)
(3)
(4)
Route of pipe-lines
Nominal diameter in inches
Date brought into use
From
To
Beryl B Platform
Beryl A Platform
20
6.7.84
Beryl A Platform
Beryl SPM 2
32
31.10.88
Beryl A Platform
Beryl SPM 3
32
31.10.87
Beryl B Platform
Subsea W. I. Well Ness 9/13–31Z
6
16.3.87
Beryl B Platform
Ness subsea Gas Lift Manifold
6
24.9.87
Beryl B Platform
Subsea W. I. Well Beryl 9/13–32 (PP)
6
1.11.87
Beryl B Platform
Subsea W. I. Well 9/13–34 (PU)
6
17.7.88
Beryl B Platform
Subsea Well Beryl 9/13–30 (PV)
6
30.11.87
Subsea Production Well Ness 9/13 – 28A
Beryl B Platform
6
11.8.87
Subsea Production Well Ness 9/13 – 38z (CA) (formally numered 9/13 – 31Z)
Beryl B Platform
6
23.2.88

---
Source: https://www.legislation.gov.uk/uksi/1989/1562/schedule/part/II (the official version)
Page: https://openlegislation.uk/submarine-pipe-lines-designated-owners-no-19-order-1989/schedule/part-II
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.