Route of pipe-lines
From
To
Nominal diameter of pipes in inches
Date brought into use
Cleeton Platform
Ravenspurn A Platform
2
24.9.89
Ravenspurn A Platform
Cleeton Platform
16
24.9.89
Ravenspurn B Platform
Subsea tee junction on pipe-line from Ravenspurn A Platform to Cleeton Platform
12
24.9.89
Ravenspurn C Platform
Subsea tee junction on pipe-line from Ravenspurn A Platform to Cleeton Platform
12
24.9.89
Subsea tee junction on pipe-line from Cleeton Platform to Ravenspurn A Platform
Ravenspurn B Platform
2
24.9.89
Subsea tee junction on pipe-line from Cleeton Platform to Ravenspurn A Platform
Ravenspurn C Platform
2
24.9.89

---
Source: https://www.legislation.gov.uk/uksi/1992/521/schedule/part/I (the official version)
Page: https://openlegislation.uk/submarine-pipe-lines-designated-owners-no-4-order-1992/schedule/part-I
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.