# The Sunderland City Council (Sunderland Strategic Transport Corridor – Temporary Works New Wear Bridge) Scheme 2009 Confirmation Instrument 2012, Note: Explanatory note


(This note is not part of the Instrument)
This instrument confirms a scheme to construct over the navigable waters of the River Wear a temporary bridge as part of the highway which is to be constructed/improved between the Wessington Way/Castletown Way roundabout and the Woodbine Terrace/Pallion New Road junction in the City of Sunderland.
The Secretary of State has modified this scheme as follows: Under “WATERWAY” the measurement “37 metres” has been amended to “27 metres”.

---
Source: https://www.legislation.gov.uk/uksi/2012/2710/note (the official version)
Page: https://openlegislation.uk/sunderland-city-council-sunderland-strategic-transport-corridor-temporary-works-new-wear-bridge-scheme-2009-confirmation-instrument-2012/note
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.