# The Sunnica Energy Farm Order 2024, Paragraph 101: Construction of the specified work

Extent: E+W

(1) The undertaker must, prior to commencement of a specified work, give to National Highways 28 days’ notice in writing of the date on which the specified work will start unless otherwise agreed by National Highways.
(2) If the carrying out of any part of the authorised development requires the booking of road space with National Highways, the undertaker must comply with National Highway’s road space booking procedures prior to and during the carrying out of the specified work and no specified work for which a road space booking with National Highways is required will commence without a road space booking having first been secured from National Highways.
(3) Any specified work must be carried out to the reasonable satisfaction of National Highways (acting reasonably) in accordance with—
(a) the relevant detailed design information and programme of works approved pursuant to paragraph 100(1) above or as subsequently varied by agreement between the undertaker and National Highways;
(b) where relevant, the DMRB, the Specification for Highway Works (contained within the Manual of Contract Documents for Highways Works) together with all other relevant standards as required by National Highways to include, inter alia, all relevant interim advice notes and any amendment to or replacement thereof for the time being in force save to the extent that any departures or exceptions from those standards apply which have been approved by National Highways; and
(c) any reasonable conditions of National Highways notified by National Highways to the undertaker pursuant to paragraph 100(4)(d) of this Part of this Schedule.
(4) The undertaker must ensure that (where possible) without entering the highway—
(a) the highway is kept free from mud, soil and litter as a result of the carrying out of a specified work; and
(b) the specified work is carried out without disturbance to the highway and so that the highway remains open for traffic at all times unless otherwise agreed with National Highways.
(5) The undertaker must permit and must require the contractor to permit at all reasonable times persons authorised by National Highways (whose identity must have been previously notified to the undertaker by National Highways) to gain access to a specified work for the purposes of inspection and supervision of a specified work or method of construction of such work.
(6) If any specified work is constructed—
(a) other than in accordance with the requirements of this Part of this Schedule; or
(b) in a way that causes damage to the highway, any highway structure or asset or any other land of National Highways,
National Highways may by notice in writing require the undertaker, at the undertaker’s own expense, to comply with the requirements of this Part of this Schedule or put right any damage notified to the undertaker under this Part of this Schedule.
(7) If within 56 days of the date on which a notice under sub-paragraph (6) is served on the undertaker, the undertaker has failed to take steps to comply with the notice, National Highways may carry out the steps required of the undertaker and may recover from the undertaker any expenditure reasonably incurred by National Highways in so doing, such sum to be payable within 30 days of demand. Where the steps required to be taken pursuant to any notice require the submission of any information for the prior approval of National Highways under paragraph 100 of this Part of this Schedule, the submission of that information will evidence that the undertaker has taken steps to comply with a notice served by National Highways under sub-paragraph (6).
(8) National Highways may, at its discretion, in its notice in writing to the undertaker given pursuant to sub-paragraph (6) state that National Highways intend to put right the damage notified to the undertaker, and if it intends to do so it must give the undertaker not less than 28 days’ notice of its intention to do so and National Highways may recover from the undertaker any reasonable expenditure incurred by National Highways in doing so.
(9) Nothing in this Part of this Schedule prevents National Highways from, in the event of an emergency or to prevent the occurrence of danger to the public, carrying out any work or taking any such action as it reasonably believes to be necessary as a result or in connection with of the carrying out of the specified works without prior notice to the undertaker and National Highways may recover from the undertaker any reasonable expenditure incurred by National Highways in so doing.

---
Source: https://www.legislation.gov.uk/uksi/2024/802/schedule/12/paragraph/101 (the official version)
Page: https://openlegislation.uk/sunnica-energy-farm-order-2024/schedule-12/paragraph-101
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.