# The Sunnica Energy Farm Order 2024, Paragraph 145: Maintenance and decommissioning

Extent: E+W

(1) Subject to sub-paragraph (2), the undertaker must not carry out any maintenance or decommissioning of the authorised development on the Campus works area, or enter upon any part of it, until it has submitted details of the proposed maintenance or decommissioning activities and measures proposed to mitigate any resulting adverse impacts on the operation of the Campus and the details have been approved by HPUT (such approval not to be unreasonably withheld or delayed and in any event to be given or refused no later than 40 working days of receipt of the written details); and—
(a) such details must (unless otherwise agreed in writing between HPUT and the undertaker) accord with the principles of the provisions in this Part of this Schedule where relevant for the purposes of maintenance or decommissioning; and
(b) the undertaker must comply with the approved details.
(2) The undertaker must not use or enter upon any part of the Campus (which for the avoidance of doubt includes the Campus access road) to carry out any maintenance or decommissioning of the authorised development except, on the terms of this Part of this Schedule, the Campus works area, unless otherwise agreed in writing between HPUT in its absolute discretion and the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2024/802/schedule/12/paragraph/145 (the official version)
Page: https://openlegislation.uk/sunnica-energy-farm-order-2024/schedule-12/paragraph-145
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.