# The Sunnica Energy Farm Order 2024, Paragraph 15: Operational environmental management plan

Extent: E+W

(1) Prior to the date of final commissioning for any phase, an operational environmental management plan for that phase must be submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of West Suffolk and the District of East Cambridgeshire, both relevant planning authorities, such approval to be in consultation with the relevant highway authority, Natural England and the Environment Agency.
(2) The operational environmental management plan submitted under sub-paragraph (1) must be substantially in accordance with the framework operational environmental management plan.
(3) The operation of the authorised development must be carried out in accordance with the approved operational environmental management plan.

---
Source: https://www.legislation.gov.uk/uksi/2024/802/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/sunnica-energy-farm-order-2024/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.