# The Sunnica Energy Farm Order 2024, Paragraph 20: Skills, supply chain and employment

Extent: E+W

(1) No phase of the authorised development may commence until a skills, supply chain and employment plan in relation to that phase has been submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of West Suffolk and the District of East Cambridgeshire, both relevant planning authorities.
(2) The skills, supply chain and employment plan submitted under sub-paragraph (1) must be substantially in accordance with the outline skills, supply chain and employment plan.
(3) The skills, supply chain and employment plan must identify opportunities for individuals and businesses to access employment and supply chain opportunities associated with the construction, operation and maintenance of the authorised development, and the means for publicising such opportunities.
(4) The skills, supply chain and employment plan must be implemented as approved and maintained throughout the construction and operation of the authorised development and during the carrying out of decommissioning works.

---
Source: https://www.legislation.gov.uk/uksi/2024/802/schedule/2/paragraph/20 (the official version)
Page: https://openlegislation.uk/sunnica-energy-farm-order-2024/schedule-2/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.