# The Sunnica Energy Farm Order 2024, Part 1: PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED

Extent: E+W

(1)
District
(2)
Public right of way
(3)
Measure
East Cambridgeshire District
35/10
From the point shown as reference PRoWC1A on sheet 3 of the traffic regulation measures plans – temporary road closures, for a distance of 90 metres in a generally north-westerly direction to the point shown as reference PRoWC1B on sheet 3 of the traffic regulation measures plans – temporary road closures.
Temporarily closed to all traffic save for traffic under the direction of the undertaker.
East Cambridgeshire District
92/19
From the point shown as reference PRoWC2A on sheet 4 of the traffic regulation measures plans – temporary road closures, for a distance of 215 metres in a generally southerly direction to the point shown as reference PRoWC2B on sheet 4 of the traffic regulation measures plans – temporary road closures.
Temporarily closed to all traffic save for traffic under the direction of the undertaker.
East Cambridgeshire District
204/1
From the point shown as reference PRoWC3A on sheet 5 of the traffic regulation measures plans – temporary road closures, for a distance of 125 metres in a generally north-easterly direction to the point shown as reference PRoWC3B on sheet 5 of the traffic regulation measures plans – temporary road closures.
Temporarily closed to all traffic save for traffic under the direction of the undertaker.
East Cambridgeshire District
49/7
From the point shown as reference PRoWC4A on sheet 11 of the traffic regulation measures plans – temporary road closures, for a distance of 115 metres in a generally north-westerly direction to the point shown as reference PRoWC4B on sheet 11 of the traffic regulation measures plans – temporary road closures.
Temporarily closed to all traffic save for traffic under the direction of the undertaker.
West Suffolk District
W-257/003/0
From the point shown as reference PRoWC5A on sheet 12 of the traffic regulation measures plans – temporary road closures, for a distance of 115 metres in a generally north-westerly direction to the point shown as reference PRoWC5B, on sheet 12 of the traffic regulation measures plans – temporary road closures.
Temporarily closed to all traffic save for traffic under the direction of the undertaker.
East Cambridgeshire District
W-257/007/0, W-257/002/X, W-257/002/0
From the point shown as reference ProWC6A on sheet 20 of the traffic regulation measures plans – temporary road closures, for a distance of 505 metres in a generally southerly direction to the point shown as reference PRoWC6B on sheet 20 of the traffic regulation measures plans – temporary road closures.
Temporarily closed to all traffic save for traffic under the direction of the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2024/802/schedule/6/part/1 (the official version)