# The Sunnica Energy Farm Order 2024, Paragraph 1: Interpretation

Extent: E+W

In this Schedule—
“access rights” means rights over land to—
alter, improve, form, maintain, retain, use (with or without vehicles, plant and machinery), remove, reinstate means of access to the authorised development including visibility splays and to remove impediments to such access; and
pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface) for all purposes in connection with the authorised development;
“cable rights” means rights over land to—
install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures;
remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and
restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;
“crane rights” means rights over land to pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface) and to temporarily remove impediments to such a passage for all purposes in connection with the authorised development;
“substation connection rights” means rights over land to—
install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures and to connect such cables and services to the National Grid Burwell substation;
install, use, support, protect, inspect, alter, remove, replace retain, renew, improve and maintain watercourses, public sewers and drains and drainage apparatus and equipment;
remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with Work Nos. 4;
restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development; and
install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain soft landscaping and biodiversity measures; and
“vegetation maintenance rights” means rights over land to install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain vegetation for all purposes in connection with the authorised development.
(1)
Plot reference number shown on the land plans
(2)
Purposes for which rights over land may be acquired and restrictive covenants imposed
. . .. . .
. . .. . .
1-04Access rights
1-05Access rights
1-06Access rights
1-07Cable rights
2-01Cable rights
3-02Access rights
3-07Access rights
3-08Access rights
3-09Access rights
3-10Cable rights
4-02Access rights
4-03Cable rights
4-04Access rights
4-05Cable rights
5-01Cable rights
5-02Cable rights and access rights
5-04Cable rights and access rights
5-08Cable rights and access rights
5-09Cable rights
5-10Cable rights and access rights
. . .. . .
6-02Cable rights and access rights
6-07Access rights
6-08Access rights
6-09Access rights
7-06Cable rights and access rights
7-07Access rights
7-09Access rights
7-10Access rights
7-11Access rights
7-12Access rights
8-02Cable rights
8-03Cable rights
8-04Cable rights
8-05Cable rights
8-06Cable rights
9-01Cable rights
9-02Cable rights
9-03Access rights
9-04Cable rights and access rights
9-05Access rights
9-06Cable rights
10-01Access rights
10-02Access rights
10-03Access rights
10-04Access rights
10-05Access rights
10-12Cable rights
10-13Cable rights
10-14Cable rights
10-15Cable rights
10-16Cable rights
10-17Cable rights
10-18Cable rights
10-19Cable rights
10-20Cable rights
10-23Access rights
10-24Access rights
10-25Access rights
10-26Access rights
10-27Access rights
10-28Access rights
10-29Cable rights
10-30Cable rights
10-31Cable rights
10-32Cable rights
10-33Cable rights
11-01Cable rights
11-02Access rights
11-03Cable rights and access rights
11-04Access rights
14-04Access rights
14-05Access rights
14-06Access rights
14-07Cable rights
14-08Cable rights and access rights
14-09Cable rights
15-01Cable rights
15-02Cable rights and access rights
15-03Cable rights
15-04Cable rights
15-05Cable rights
15-12Cable rights
16-01Cable rights
16-02Cable rights
16-03Cable rights
16-04Cable rights
16-07Cable rights
16-08Cable rights
16-09Cable rights
16-10Cable rights
16-11Cable rights
16-12Access rights
16-13Access rights
16-14Cable rights ...
16-15Cable rights and access rights
16-16Cable rights
16-17Cable rights
16-18Cable rights
16-19Cable rights
16-20Access rights
17-01Cable rights
17-02Access rights
17-03Cable rights
18-01Cable rights
18-02Cable rights and access rights
18-03Cable rights and access rights
18-04Cable rights and access rights
18-05Access rights
18-06Access rights
18-07Cable rights
18-08Cable rights
18-09Cable rights
18-10Cable rights
18-11Cable rights and access rights
18-12Cable rights and access rights
18-13Cable rights
18-14Cable rights
18-15Cable rights
18-16Cable rights and access rights
18-17Cable rights
18-18Cable rights
18-19Cable rights
19-01Cable rights
19-02Cable rights
19-03Cable rights
19-04Cable rights
19-05Cable rights
19-06Cable rights
19-07Cable rights
19-08Cable rights
19-09Cable rights
19-10Cable rights
19-11Cable rights
19-12Cable rights and access rights
19-13Cable rights and access rights
19-14Access rights
19-15Access rights
20-01Cable rights
20-02Cable rights
20-03Cable rights
20-04Cable rights
20-05Access rights
20-06Access rights
20-07Access rights
20-08Cable rights
20-09Cable rights
20-10Cable rights
20-11Cable rights
20-12Cable rights
20-13Substation connection rights and access rights
20-14Substation connection rights
20-15Substation connection rights and access rights
20-16Substation connection rights
20-17Substation connection rights
20-18Substation connection rights
20-19Substation connection rights
20-20Substation connection rights
20-21Substation connection rights and access rights
20-22Substation connection rights
20-23Substation connection rights
20-24Substation connection rights
20-25Substation connection rights
20-26Substation connection rights
20-27Substation connection rights
20-28Substation connection rights
20-29Substation connection rights
20-30Substation connection rights
21-01Crane rights
21-02Crane rights
21-03Crane rights
22-01Crane rights

---
Source: https://www.legislation.gov.uk/uksi/2024/802/schedule/8/paragraph/1 (the official version)
Page: https://openlegislation.uk/sunnica-energy-farm-order-2024/schedule-8/paragraph-1/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.