Regulation 10 Release of non-performance bond where duty to adopt does not apply
Except where paragraph (3) applies, an approving body must release a non-performance bond within 4 weeks beginning on the first working day after completion of a drainage system that is constructed in accordance with approved proposals.
Paragraph (3) applies if the approving body—
issued a certificate under paragraph 12(2) of Schedule 3, and
carried out work to ensure the drainage system was completed in such a manner as to make it likely to operate in compliance with national standards.
The approving body must, within 4 weeks beginning on the first working day after completing the work—
send to the developer a full account of any sums received under the bond that have been applied to the expense of carrying out the work,
pay the developer any excess, and
release the non-performance bond.
In this regulation—
-
“approved proposals” (“cynigion a gymeradwywyd”) means proposals approved under paragraph 7(1) of Schedule 3, including any conditions of approval;
-
“drainage system” (“system ddraenio”) is to be construed as a drainage system to which the duty to adopt does not apply.