# The Sustainable Drainage (Approval and Adoption Procedure) (Wales) Regulations 2018, Regulation 16: Requirement to undertake remedial work


(1) If a statutory undertaker fails to carry out reconstruction work in accordance with the confirmed proposal, the approving body may require the undertaker to carry out remedial work within a specified timescale.
(2) If a statutory undertaker fails to comply with a requirement under paragraph (1), the approving body may—
(a) carry out remedial work, and
(b) recover as a debt from the undertaker any costs incurred in carrying out that work.

---
Source: https://www.legislation.gov.uk/wsi/2018/1077/regulation/16 (the official version)
Page: https://openlegislation.uk/sustainable-drainage-approval-and-adoption-procedure-wales-regulations-2018/regulation-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.