# The Swansea Bay Tidal Generating Station Order 2015, Article 54: Provisions for effect of Adaptive Environmental Management Plan

Extent: E+W

(1) Where any Requirement provides for an AEMP as defined in Part 3 of Schedule 1, and any provision of that AEMP makes matters of dispute between the undertaker, any relevant planning authority and Natural Resources Wales subject to arbitration under this Order, article 50 (arbitration) applies.
(2) Where under the terms of an AEMP it is necessary for the officers of any relevant planning authority or Natural Resources Wales to attend any meetings of any group or to review any documents, the undertaker is liable for the reasonable and proper costs of those officers in respect of those activities.

---