# The Swansea Bay Tidal Generating Station Order 2015, Paragraph 15: Electrical grid connection works

Extent: E+W

(1) No part of Work No. 5a is to be commenced until—
(a) details of the buried depths of the cable comprised in those works according with the recommendations contained in the ERA report; and
(b) a scheme and programme for the works, including necessary construction details and locations of laydown areas, with details of specific ecological mitigation; and
(c) a scheme for the restoration monitoring and aftercare of areas of land disturbed by the construction of those works upon their completion including providing for the areas to be suitable for access by the public,
have been submitted to and approved by the relevant planning authority in consultation with Natural Resources Wales.
(2) Work No. 5a must be carried out in accordance with the approved details and scheme.
(3) In this Requirement, the “ERA report” means ERA report 2015 - 0265 certified as such by the Secretary of State for the purposes of this Order.

---
Source: https://www.legislation.gov.uk/uksi/2015/1386/schedule/1/paragraph/15 (the official version)
Page: https://openlegislation.uk/swansea-bay-tidal-generating-station-order-2015/schedule-1/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.