(1) No part of the authorised development is to commence until a written scope of work required for the retention (where reasonably practicable), or (as the case may be in relation to paragraph (b)) relocation, and enhancement of historic assets identified in the written scope of work, including in particular—
(a) the standing pill boxes, gun emplacement and tank traps situated seaward of Queen’s Dock Swansea, with a buffer zone of 5m, together with suitable landscape treatment; and
(b) the navigation light situated on the existing Swansea Harbour East Pier,
has been submitted to and approved by the relevant planning authority in consultation with Cadw and the Glamorgan-Gwent Archaeological Trust Ltd.
(2) The authorised development is to be carried out in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2015/1386/schedule/1/paragraph/17 (the official version)
Page: https://openlegislation.uk/swansea-bay-tidal-generating-station-order-2015/schedule-1/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.