# The Swansea Bay Tidal Generating Station Order 2015, Paragraph 19: Piling

Extent: E+W

(1) No piling activities relating to those works shown on drawing TLP - SWANSEA BAY - 141003 - VO.2 as certified by the Secretary of State are to commence until a piling method statement according with the annotations of that drawing has been submitted to and approved by the relevant planning authorities in consultation with Natural Resources Wales.
(2) Piling must be carried out in accordance with the approved method statement.

---
Source: https://www.legislation.gov.uk/uksi/2015/1386/schedule/1/paragraph/19 (the official version)
Page: https://openlegislation.uk/swansea-bay-tidal-generating-station-order-2015/schedule-1/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.