# The Swansea Bay Tidal Generating Station Order 2015, Paragraph 60: Arbitration

Extent: E+W

Save for differences or disputes arising under paragraphs 52(2), 52(4), 53(1) and 54 any difference or dispute arising between the undertaker and the protected person under this Part shall, unless otherwise agreed in writing between the undertaker and that protected person, be determined by arbitration in accordance with article 50 (arbitration).

---