# The Tees Combined Cycle Power Plant Order 2019, Paragraph 14: Waste management during construction


(1) No phase of the authorised development may commence other than preliminary works until the relevant planning authority has received and approved in writing a waste management plan relating to the construction of that phase of the authorised development.
(2) The plan must incorporate the principles in and be based on the draft waste management plan contained in Annex D4 of the environmental statement and must address and include at least the following—
(a) the storage of waste materials on site;
(b) removal of waste materials from the site for recovery or disposal at appropriately licensed sites;
(c) a materials management plan;
(d) a sediment control plan; and
(e) monitoring measures.
(3) The approved waste management plan must be implemented as approved and maintained during construction of that phase of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2019/827/schedule/1/paragraph/14 (the official version)
Page: https://openlegislation.uk/tees-combined-cycle-power-plant-order-2019/schedule-1/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.