(1) With respect to any requirement which requires the authorised development or any part of it to be carried out in accordance with the details, thresholds, plans or schemes approved under this Schedule, the approved details, thresholds, plans or schemes are, subject to sub-paragraph (2), taken to include any amendments or variations that may subsequently be approved in writing by the relevant planning authority in consultation with any other consultee specified in the requirement in question, or approved in writing by the relevant planning authority or another approval authority.
(2) Any amendments to or variations from any details, thresholds, plans or schemes approved pursuant to these requirements must be minor or immaterial and in order to obtain approval to such amendments or variations it must be demonstrated to the reasonable satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2019/827/schedule/1/paragraph/27 (the official version)
Page: https://openlegislation.uk/tees-combined-cycle-power-plant-order-2019/schedule-1/paragraph-27
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.