# The Telford Railfreight Terminal (Donnington) Order 2005, Paragraph 4


(1) Any specified work and any protective work to be constructed by virtue of paragraph 3(4) above shall when constructed be constructed—
(a) with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled under paragraph 3(1) above;
(b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
(c) in such manner as to cause as little damage as is possible to railway property; and as little interference as may be with the conduct of traffic on the railways of the company;
and, if any damage to railway property on any such interference or obstruction shall be caused by the carrying out of, or in consequence of the construction of a specified work, the Council shall, notwithstanding any such approval, make good such damage and shall pay to the company all reasonable expenses to which the company may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
(2) The Council shall give to the engineer not less than 90 days' notice of its intention to commence the construction of a specified work and shall give, except in emergency (when it shall give such notice as may be reasonably practicable), 90 days' notice of its intention to carry out any works for the maintenance or repair of a specified work in so far as such work of repair or maintenance may affect railway property.

---
Source: https://www.legislation.gov.uk/uksi/2005/1163/schedule/9/paragraph/4 (the official version)
Page: https://openlegislation.uk/telford-railfreight-terminal-donnington-order-2005/schedule-9/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.