Article 2 Authorisation of works
(1)
The Authority may continue and maintain in, on or under the land described in Schedule 1 the existing borehole 585mm in diameter and (in addition to the works authorised by Section 4 of the Third Schedule as applied to the undertaking by this Order) may construct and maintain in, on or under the said land all such additional wells, boreholes, adits and headings as may be necessary or expedient for augmenting, improving or maintaining the supply of water obtainable by means of the said borehole.
(2)
The works authorised by this Order shall for all purposes form part of the undertaking.