Explanatory note

Original text. Later amendments are not shown.

(This note is not part of the Order)

The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I 2014/2384) (“the 2014 Order”) granted development consent within the meaning of the Planning Act 2008 (c. 29).

Following an application made under paragraph 2 of Schedule 6 to the Planning Act 2008, this Order makes the following non-material changes to the 2014 Order—

(a)

Part 4 of Schedule 2 is amended so as to—

(i)

revise the areas within which certain permanent works can take place under two of the Site Works Parameters Plans;

(ii)

revise two of the Extent of Loss of Listed River Wall plans in order to show a change in the area and extent of loss; and

(iii)

make consequential changes consistent with the other revised plans to two of the Demolition and Site Clearance plans, and to include an additional area for potential ground strengthening works.

(b)

Schedule 3 is amended so as to make consequential changes to Ref BLABF11 in light of the revised plans.

Following certification under article 3 of this Order (certification of plans, etc.), a copy of the substituted plans mentioned in this Order may be inspected free of charge during working hours at the offices of Westminster City Council, 64 Victoria Street, London, SW1E 6QP or The City of London Corporation, Guildhall, Aldermanbury, London, EC2V 7HH (as relevant).

A full impact assessment has not been produced for this instrument as no, or no significant, impact on the private, voluntary or public sector is foreseen.