The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (“2014 Order”) granted development consent within the meaning of the Planning Act 2008 (c. 29).

Following an application made under paragraph 2 of Schedule 6 to the Planning Act 2008, this Order makes the following non-material change to the 2014 Order. Schedule 2, Part 4 of the 2014 Order is amended to resolve ambiguities identified on the Site works parameters plan for the Falconbrook Pumping Station Site and to allow the works to be constructed as proposed in the original application for development consent.

A full impact assessment has not been produced for this instrument as no, or no significant, impact on the private, voluntary or public sector is foreseen.