Explanatory note

Original text. Later amendments are not shown.

(This note is not part of the Order)

The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I 2014/2384) (“the 2014 Order”) granted development consent within the meaning of the Planning Act 2008 (c. 29).

Following an application made under paragraph 2 of Schedule 6 to the Planning Act 2008, this Order makes the following non-material changes to the 2014 Order—

(a)

Part 1 of Schedule 1 is amended to make changes to Work No 16c (xi) and Work No 16c (xii) to remove reference to temporary and permanent moorings and refer only to a permanent mooring for the Tattershall Castle, and to provide for the permanent removal of the service mooring previously used by City Cruises Limited;

(b)

Part 4 of Schedule 2 is amended so as to—

(i)

revise the Demolition and site clearance plan (sheet 2 of 2) to show the permanent removal of the service mooring;

(ii)

revise the area within which certain permanent works can take place under the Site works parameter plan;

(iii)

revise the Proposed site features plan and Proposed landscape plan (sheet 2 of 2) to show only one vessel mooring location;

(iv)

remove the vessel mooring from the Proposed landscape plan (sheet 1 of 2);

(v)

remove the note below ‘Detail Section’ on the Proposed mooring access details plan;

(vi)

revise the location of the relocated vessel and remove the maximum permanent extent of loss of listed river wall on the As existing and proposed river elevation impact on listed structure plan (sheet 1 of 2).

(c)

Schedule 3 is amended to amend the drawing numbers referred to in site specific Requirements VCTEF3, VCTEF4, VCTEF7, VCTEF10 and VCTEF15, and amend the titles of VCTEF3 and VCTEF11 for the Victoria Embankment Foreshore site;

(d)

Schedule 5 is amended to remove reference to temporary and permanent moorings and refer only to a new mooring for the Tattershall Castle.

A copy of the substituted plans mentioned in this Order and certified in accordance with article 3 of this Order (certification of plans, etc.) may be inspected free of charge during working hours at the offices of Westminster City Council, 64 Victoria Street, London, SW1E 6QP.

A full impact assessment has not been produced for this instrument as no, or no significant, impact on the private, voluntary or public sector is foreseen.