Schedule 1 Amendments to Schedule 1 to the 2014 Order

Original text. Later amendments are not shown.

Provision to be amendedCurrent textText to be substituted for the current text
Schedule 1, Part 1 (“Authorised Development”) Work No. 16c (xi)“(xi) removal of existing mooring for the Tattershall Castle attached to listed wall (and associated access ramps), construction and use of a new temporary and permanent mooring (over listed wall) for a vessel to the south of Work No. 16c(ii), and means of access for both attached to the listed wall including access brows, gangways, guide piles, mooring chains and anchors fixed to the river bed, construction dredging and associated sheet piling to accommodate the relocated vessel in both the permanent and temporary locations for the vessel;”“(xi) removal of existing mooring for the Tattershall Castle attached to listed wall (and associated access ramps), construction and use of a new mooring (over listed wall) for a vessel to the south of Work No. 16c(ii), and means of access attached to the listed wall including access brows, gangways, guide piles, mooring chains and anchors fixed to the river bed, construction dredging and associated sheet piling to accommodate the relocated vessel;”
Schedule 1, Part 1 (“Authorised Development”) Work No. 16c (xii)“(xii) temporary removal and then reinstatement of the service mooring / service pontoon to the east of the junction of Victoria Embankment and Horse Guards Avenue including guide piles;”“(xii) permanent removal of the service mooring / service pontoon to the east of the junction of Victoria Embankment and Horse Guards Avenue including guide piles;”