# The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014, Paragraph 21: Notice of Determination

Extent: E+W

(1) Subject to condition 21 (2) or (3), the MMO shall give notice to the licence holder of the determination of the application within 35 business days of the day immediately following that on which the application is received by the MMO.
(2) Where the MMO has made a request under paragraph 19, the MMO shall give notice to the licence holder of the determination of the application no later than 65 business days of the day immediately following that on which the application is received by the MMO.
(3) The MMO and the licence holder may agree in writing a longer period of time for the provision by the MMO of a notice under condition 21(1) such period to be no more than 65 days from the day immediately following that on which the application is received.
(4) Where the MMO refuses the application the refusal notice must state the reasons for the refusal.
(5) Where notice is not given by the MMO in accordance with condition 21(1) or (2) the application is deemed to have been refused.

---
Source: https://www.legislation.gov.uk/uksi/2014/2384/schedule/15/paragraph/21 (the official version)
Page: https://openlegislation.uk/thames-water-utilities-limited-thames-tideway-tunnel-order-2014/schedule-15/paragraph-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.