# The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014, Paragraph 18: Arbitration

Extent: E+W

Any difference or dispute arising between the promoter and an undertaker under this Schedule shall, unless otherwise agreed in writing between the promoter and that undertaker, be determined by arbitration in accordance with article 63 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2014/2384/schedule/16/part/1/chapter/1/paragraph/18 (the official version)
Page: https://openlegislation.uk/thames-water-utilities-limited-thames-tideway-tunnel-order-2014/schedule-16/part-1/chapter-1/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.