# The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014, Paragraph 7: Protection of drainage works and flood defences

Extent: E+W

Save as may be authorised by this Order the undertaker shall not damage or obstruct any drainage works during the construction of the specified works.

---
Source: https://www.legislation.gov.uk/uksi/2014/2384/schedule/16/part/3/paragraph/7 (the official version)
Page: https://openlegislation.uk/thames-water-utilities-limited-thames-tideway-tunnel-order-2014/schedule-16/part-3/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.