# The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014, Paragraph 5

Extent: E+W

(1) The undertaker shall give to the engineer not less than 56 days’ notice of its intention to commence the construction of any of the specified works and also, except in an emergency (when they shall give such notice as may be reasonably practicable), of its intention to carry out any such works for the repair or maintenance of the specified works in so far as such works of repair or maintenance affect or interfere with the piers.
(2) The specified works shall, when commenced, be carried out with all reasonable dispatch in accordance with the plans approved or deemed to be approved or settled as aforesaid and under the supervision (if given), and to the reasonable satisfaction, of the engineer, and in such manner as to cause as little damage as may be to the piers and as little interference as may be with the conduct of LRSL’s operation and the use by passengers or customers of the piers and, if any damage to the piers or any such interference is caused by the carrying out of the specified works, the undertaker shall, notwithstanding any such approval as aforesaid, make good such damage and shall pay to LRSL all reasonable expenses to which it may be put and compensation for any loss which they may sustain by reason of any such damage or interference.
(3) Nothing in this paragraph shall impose any liability on the undertaker with respect to any damage, cost, expense or loss to the extent that such damage, cost, expense or loss is attributable to the act, neglect or default of LRSL or its servants or agents.

---
Source: https://www.legislation.gov.uk/uksi/2014/2384/schedule/16/part/4/chapter/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/thames-water-utilities-limited-thames-tideway-tunnel-order-2014/schedule-16/part-4/chapter-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.