# The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014, Schedule 5: STREETS SUBJECT TO ALTERATION OF LAYOUT

Extent: E+W

Borough
Street to be altered
Description of alteration
Relevant Site
London Borough of Ealing
Canham Road
Works to provide site access, temporary removal of on street parking, introduction of temporary waiting restrictions and footway widening works.
Acton Storm Tanks
London Borough of Ealing
Warple Way
Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions
Acton Storm Tanks
London Borough of Ealing
Stanley Gardens
Works associated with the temporary modification to kerb line, temporary removal of on street parking and introduction of temporary waiting restrictions
Acton Storm Tanks
London Borough of Hammersmith and Fulham
Distillery Road
Works to provide site accesses
Hammersmith Pumping Station
London Borough of Hammersmith and Fulham
Chancellor’s Road
Temporary removal of on street parking and introduction of temporary waiting restrictions. Modification to kerb line on its junction with Distillery Road
Hammersmith Pumping Station
London Borough of Wandsworth
The Embankment
Works to provide site access, temporary removal of on street parking, the introduction of temporary waiting restrictions, formation of access to temporary slipway, temporary suspension of one-way, kerb line modifications and temporary removal of traffic island
Putney Embankment Foreshore
Works associated with environmental enhancement including footway surfacing and street furniture
London Borough of Wandsworth
Glendarvon Street
Temporary removal of on street parking and introduction of waiting restrictions
Putney Embankment Foreshore
London Borough of Wandsworth
Lower Richmond Road
Installation of ducting within carriageway and pedestrian site access gate
Putney Embankment Foreshore
London Borough of Wandsworth
Putney High Street/Putney Bridge
Installation of vent column
Putney Embankment Foreshore
Hammersmith and Fulham
Carnwath Road
Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions, footway and junction modifications at its junction with Wandsworth Bridge Road
Carnwath Road Riverside
Hammersmith and Fulham
Wandsworth Bridge Road
Modification to traffic signalised junction
Carnwath Road Riverside
London Borough of Wandsworth
Dormay Street
Works to provide site access
Dormay Street
London Borough of Wandsworth
The Causeway
Works to provide site access
Temporary removal of on street parking and introduction of temporary waiting restrictions
Dormay Street
London Borough of Wandsworth
Armoury Way
Temporary kerb line and junction modifications
Dormay Street
London Borough of Wandsworth
Neville Gill Close
Provision of construction access, temporary modification to kerb lines and pedestrian refuge
King George’s Park
London Borough of Wandsworth
Buckhold Road
Modification to kerb lines, pedestrian refuge and park entrance
King George’s Park
London Borough of Wandsworth
York Road
Works to provide site accesses and works associated with the relocation of bus stop facilities
Falconbrook Pumping Station
London Borough of Wandsworth
York Gardens
Woks to provide site access and temporary removal of parking
Falconbrook Pumping Station
Royal Borough of Kensington and Chelsea
Lots Road
Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions
Cremorne Wharf Depot
Royal Borough of Kensington and Chelsea
Chelsea Embankment
Works to provide site accesses
Works to facilitate the provision of traffic management including provision of a temporary formal crossing, temporary removal of traffic island, provision of site hoarding
Works associated with environmental enhancement including footway surfacing and street furniture
Chelsea Embankment Foreshore
Royal Borough of Kensington and Chelsea
The Bull Ring
Works associated with environmental enhancement including footway and carriageway surfacing and street furniture
Chelsea Embankment Foreshore
London Borough of Wandsworth
Kirtling Street
Works to provide site access, the provision of traffic management, temporary removal of on street parking and introduction of temporary waiting restrictions
Works to undertake environmental enhancements
Kirtling Street
London Borough of Wandsworth
Cringle Street
Works to provide site access
Works to undertake carriageway crossing for services
Works associated with environmental enhancement including footway surfacing and street furniture
Kirtling Street
London Borough of Wandsworth
Nine Elms Lane
Works to provide site access
Works associated with environmental enhancement including footway surfacing, tree planting, and street furniture
Heathwall Pumping Station
London Borough of Lambeth
Albert Embankment
Works to provide site access
Albert Embankment Foreshore
City of Westminster
Victoria Embankment
Works to provide site access.
Works to facilitate the provision of traffic management, modification to waiting restrictions, removal of central carriageway reserve, provision of site hoarding, removal of cycle parking station
Works to facilitate the provision of access to boat moorings
Works associated with environmental enhancement including footway surfacing and street furniture
Works to construct a ramp and stairs on the footway
Victoria Embankment Foreshore
City of London
Victoria Embankment / Blackfriars Underpass / Blackfriars Bridge head / Blackfriars Bridge
Works to provide site access.
Provision of traffic management including modification to waiting restrictions/loading bays, provision of site hoarding
Works to facilitate the temporary and permanent provision of access to boat moorings
Works associated with environmental enhancement including footway surfacing, step access from Blackfriars Bridge, lift access from Blackfriars Bridge, and street furniture
Works to construct a ramp and stairs on the footway
Blackfriars Bridge Foreshore
City of London
New Bridge Street / Blackfriars Bridge / Blackfriars Bridge head
Provision of Temporary traffic management
Provision of pedestrian lift
Blackfriars Bridge Foreshore
City of London
White Lion Hill
Modification of kerb, boundary wall, railing and provision of loading bay
Blackfriars Bridge Foreshore
London Borough of Southwark
Maguire Street and Shad Thames
Works to provide site access
Works for the provision of traffic management, provision of temporary turning head, temporary removal of on street parking, introduction of temporary waiting restrictions and works for the provision of chambers, pipeline and ducts
Shad Thames Pumping Station
London Borough of Southwark
Gainsford Street
Works for the provision of in sewer equipment
Shad Thames Pumping Station
London Borough of Southwark
Chambers Street
Works to provide site access
The temporary removal of on street parking and introduction of temporary waiting restrictions
Chambers Wharf
London Borough of Southwark
Loftie Street
Works to provide site access
Chambers Wharf
London Borough of Southwark
Bevington Street
The temporary removal of on street parking and introduction of temporary waiting restrictions, provision of temporary pedestrian refuge
Chambers Wharf
London Borough of Southwark
Croft Street
The temporary removal of on street parking and introduction of temporary waiting restrictions modification to traffic calming features
Service connection to existing sewer
Earl Pumping Station
London Borough of Southwark
Chilton Grove
Works to provide site access and service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions
Earl Pumping Station
London Borough of Lewisham
Croft Street
Works to provide site access
The temporary removal of on street parking and introduction of temporary waiting restrictions, modification to traffic calming features.
Service connection to existing sewer
Earl Pumping Station
London Borough of Lewisham
Yeoman Street
Works to provide site access, service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions
Earl Pumping Station
London Borough of Lewisham
Chilton Grove
Works to provide site access, service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions
Earl Pumping Station
London Borough of Lewisham
Deptford Church Street
Works associated with the temporary suspension of the pedestrian crossing, provision of temporary pedestrian crossing, temporary removal of central carriageway divide, temporary removal of bus lanes. Temporary relocation of bus stops introduction of temporary waiting restrictions
Works associated with environmental enhancement including footway surfacing and street furniture
Deptford Church Street
London Borough of Lewisham
Coffey Street
Works to provide site access
Temporary removal of on street parking and introduction of temporary waiting restrictions
Works associated with temporary one way use, including associated signs
Works associated with environmental enhancement including footway surfacing and street furniture
Deptford Church Street
London Borough of Lewisham
Crossfield Street
Works to provide site access
Temporary removal of on street parking and introduction of temporary waiting restrictions.
Works associated with temporary one way use, including associated signs
Works to form a temporary traffic management system and emergency evacuation point
Works associated with the provision of a temporary section of carriageway linking Crossfield Road to Coffey Street
Works associated with environmental enhancement including footway surfacing and street furniture
Deptford Church Street
Royal Borough of Greenwich
Norman Road
Works to provide site access
Greenwich Pumping Station
Royal Borough of Greenwich
Greenwich High Road
Works to provide site access
Greenwich Pumping Station
Royal Borough of Greenwich
Unnamed pedestrian/cycle route between Norman Road and Creekside
Temporary diversion of route and associated works
Greenwich Pumping Station
London Borough of Tower Hamlets
Glamis Road
Works to provide site access
Temporary removal of on street parking and introduction of temporary waiting restrictions, modification to traffic signal stop lines
King Edward Memorial Park Foreshore
London Borough of Tower Hamlets
Bekesbourne Street
Temporary removal of on street parking and introduction of temporary waiting restrictions, provision of construction area, provision of plant (control kiosk)
Bekesbourne Street
London Borough of Tower Hamlets
Ratcliffe Lane
Provision of construction area, provision of plant (vent pipe), temporary removal of on street parking and introduction of temporary waiting restrictions
Bekesbourne Street
London Borough of Newham
Gay Road
Works to provide site access, temporary removal of on street parking, and the introduction of temporary waiting restrictions
Abbey Mills Pumping Station
London Borough of Newham
Abbey Lane
Temporary removal of on street parking and introduction of temporary waiting restrictions
Abbey Mills Pumping Station
London Borough of Newham
Jenkins Lane
Works to provide construction / permanent site access
Beckton Sewage Treatment Works

---
Source: https://www.legislation.gov.uk/uksi/2014/2384/schedule/5 (the official version)
Page: https://openlegislation.uk/thames-water-utilities-limited-thames-tideway-tunnel-order-2014/schedule-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.