The undertaker may, in connection with the carrying out of the authorised development, temporarily stop up, alter or divert each of the public rights of way specified in column (2) of Schedule 3 (public rights of way to be temporarily stopped up) to the extent specified in column (3), by reference to the public rights of way plan.

---