  "url": "https://openlegislation.uk/thorpe-marsh-gas-pipeline-order-2016/schedule-1/paragraph-12",
  "json_url": "https://openlegislation.uk/thorpe-marsh-gas-pipeline-order-2016/schedule-1/paragraph-12.json",
  "legislation": "uksi/2016/297",
  "legislation_title": "The Thorpe Marsh Gas Pipeline Order 2016",
  "legislation_url": "https://openlegislation.uk/thorpe-marsh-gas-pipeline-order-2016",
  "path": "schedule/1/paragraph/12",
  "kind": "paragraph",
  "number": "12",
  "heading": "Public rights of way",
  "text": "(1) No stage of the authorised development may commence that would affect any public right of way until, following consultation with the relevant highway authority, a written plan based upon the outline public rights of way plan for the temporary closure, diversion (where appropriate) and re-opening of the right of way has been submitted to and approved in writing by the relevant planning authority.\n(2) The temporary closure, re-opening or diversion of the relevant right of way must be carried out in accordance with the approved plan.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 2 para. 12 in force at 25.3.2016, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2016/297/schedule/1/paragraph/12",
    "retrieved_at": "2026-10-28T23:26:11.700628+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}