# The Thorpe Marsh Gas Pipeline Order 2016, Paragraph 12: Public rights of way

Extent: E+W+S

(1) No stage of the authorised development may commence that would affect any public right of way until, following consultation with the relevant highway authority, a written plan based upon the outline public rights of way plan for the temporary closure, diversion (where appropriate) and re-opening of the right of way has been submitted to and approved in writing by the relevant planning authority.
(2) The temporary closure, re-opening or diversion of the relevant right of way must be carried out in accordance with the approved plan.

---
Source: https://www.legislation.gov.uk/uksi/2016/297/schedule/1/paragraph/12 (the official version)
Page: https://openlegislation.uk/thorpe-marsh-gas-pipeline-order-2016/schedule-1/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.