# The Thorpe Marsh Gas Pipeline Order 2016, Paragraph 15: Archaeology

Extent: E+W+S

(1) No stage of the authorised development must commence until for that stage a written scheme for the investigation of areas of archaeological interest as identified in the environmental statement has, after consultation with Doncaster Metropolitan Borough Council, East Riding of Yorkshire Council and their respective archaeological advisors or North Yorkshire County Council (as appropriate) and English Heritage, been submitted to and approved in writing by the relevant planning authority.
(2) The scheme must identify areas where an agreed scheme of archaeological works is required and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found and must include an implementation timetable.
(3) Any archaeological works carried out under the scheme must be carried out by a suitably qualified person or body and approved by the relevant planning authority.
(4) Any archaeological works must be carried out in accordance with the approved scheme.

---
Source: https://www.legislation.gov.uk/uksi/2016/297/schedule/1/paragraph/15 (the official version)
Page: https://openlegislation.uk/thorpe-marsh-gas-pipeline-order-2016/schedule-1/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.