(1) The construction of the AGI site must not commence until written details of the permanent external lighting to be installed at the AGI site, measures to prevent light spillage and measures to regulate the times at which the permanent external lighting may operate have been submitted to and approved in writing by the relevant planning authority.
(2) The authorised development must be operated in accordance with the approved details.

---