# The Thorpe Marsh Gas Pipeline Order 2016, Paragraph 16: Arbitration

Extent: E+W+S

Save for differences or disputes arising under paragraphs 6(2) and (4), 7(1), 8 and 9, any difference or dispute arising between the undertaker and a protected person under this Part must, unless otherwise agreed in writing between the undertaker and that protected person, be determined by arbitration in accordance with article 42 (arbitration).

---