# The Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024

S.I. 2024/955 · made 12 September 2024

This Order amends the Thurrock Flexible Generation Plant Development Consent Order 2022, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order gives flexibility in the delivery of the gas reciprocating engine element of the gas fired electricity generating station.

Made under: Planning Act 2008 (Schedule 6 paragraph 2)

PDFs: Printed copy https://openlegislation.uk/thurrock-flexible-generation-plant-consent-amendment-no-2-order-2024/pdf/uksi_20240955_en.pdf

## Introductory text

Infrastructure Planning
Made 12th September 2024
Coming into force 13th September 2024
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for a non-material change to the Thurrock Flexible Generation Plant Development Consent Order 2022.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations , has decided to make the change on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:

## 1 Citation and commencement

This Order may be cited as the Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024 and comes into force on 13th September 2024.

## 2 Amendment to the Thurrock Flexible Generation Plant Development Consent Order 2022

The Thurrock Flexible Generation Plant Development Consent Order 2022 (“the 2022 Order”) is amended in accordance with this Order.

## 3 Amendment to Schedule 1 (Authorised Development)

In Schedule 1 to the 2022 Order (Authorised Development), in the description of Work no. 1 in 1A replace at 1A(b) “up to 48 gas reciprocating engines” with “up to 96 gas reciprocating engines”.

## Signature

Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery
Department for Energy Security and Net Zero
12th September 2024

## Explanatory note

(This note is not part of the Order)
This Order amends the Thurrock Flexible Generation Plant Development Consent Order 2022, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order gives flexibility in the delivery of the gas reciprocating engine element of the gas fired electricity generating station.

---
Source: https://www.legislation.gov.uk/uksi/2024/955 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-consent-amendment-no-2-order-2024
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.